I. Pre-Installation Preparations
1. Technical Preparations
Prior to construction, a drawing review meeting must be conducted, focusing on verifying the design parameters of the grounding system, including grounding electrode specifications, burial depth requirements, and target grounding resistance values. Additionally, specialized technical briefing documents must be prepared to ensure that workers clearly understand the process standards and safety requirements.
2. Material Selection
Grounding electrode materials must possess good electrical conductivity and corrosion resistance. Common material specifications are as follows:
In coastal or humid areas, it is recommended to use copper-clad steel grounding electrodes to enhance corrosion resistance. The use of rebar as grounding electrode material is strictly prohibited, as its ribbed surface can easily cause tip-concentrated discharge and it corrodes rapidly.
3. Equipment Preparation
The main construction equipment includes: an electric hammer drill (≥1200 W), hydraulic pliers, a digital ground resistance tester (resolution 0.01 Ω), an arc welder, exothermic welding molds, etc.
II. Selection of Grounding Electrode Location
The selection of the grounding electrode location directly affects the effectiveness of the grounding system and the convenience of future maintenance. The following principles should be followed:
III. Grounding Electrode Construction Procedures
1. Excavation of Grounding Trench
A combination of mechanical excavation and manual finishing is used. The dimensions of the main grounding trench are generally 500 mm wide by 800 mm deep. The trench bottom must be leveled and compacted; if rocky strata are encountered, they should be backfilled with fine soil (thickness ≥ 300 mm). Backfill soil must be free of foreign materials such as rocks and construction debris; soil sourced from outside the site must not be highly corrosive.
2. Driving in Grounding Electrodes
Requirements for the burial depth of a single electrode:
Soil Type
Depth from Ground Surface to Top
Remarks
Ordinary Clay
≥0.6 m
Standard conditions
Gravel
≥1.0 m
Requires replacement with clay and addition of a resistance-reducing agent
Corrosive Soil
≥1.2 m
Use copper-clad steel or thickened galvanized steel
Key Points for Driving:
3. Arrangement of Multiple Grounding Electrodes
When a single grounding electrode cannot meet the resistance requirements, multiple grounding electrodes must be installed:
4. Welding and Connections
The connection between grounding conductors and grounding electrodes shall be made using lap welding; the quality of the weld directly determines the reliability of the grounding system:
Weld treatment: The weld height must be ≥ 4 mm; after welding, remove slag and apply anti-corrosion treatment
5. Enclosure Grounding Connections
Special attention must be paid to the connection between the grounding busbar and the DFW low-voltage branch box:
6. Corrosion Protection
IV. Ground Resistance Testing and Acceptance
1. Resistance Testing
After installation is complete, actual measurements must be taken using a ground resistance tester:
2. Corrective Actions for Excessive Resistance
If the measured resistance value exceeds the standard, the following measures may be taken:
3. Acceptance Inspection
During acceptance, the following inspections shall be conducted and relevant documentation submitted:
V. Safety Precautions
1. Before installation, ensure that the upstream switch is turned off and verify that the circuit is de-energized; operators must wear insulated protective gear.
2. Do not perform outdoor work in rainy weather; the ambient temperature must be ≥5°C, and relative humidity must be ≤85%.
3. Set up barriers and warning signs at the site; illuminance during nighttime work must be ≥50 lx.
4. Inspect grounding connection points at least once a year for corrosion or looseness; recheck grounding resistance after rainfall.
5. Install sturdy protective sleeves, such as steel pipes, where grounding wires pass through walls or floors.
6. Install expansion joints when grounding wires cross building expansion joints or settlement joints (the grounding wire itself may be bent into an arc to serve as a substitute).
VI. Summary
The installation of grounding electrodes for DFW low-voltage branch boxes is a systematic project involving multiple stages, including material selection, location planning, construction techniques, and testing and acceptance. The key points can be summarized as follows: burial depth ≥ 0.6 m, spacing ≥ 5 m, welding specifications, independent connections, and resistance ≤ 4 Ω. Only by strictly adhering to the specifications during construction can the long-term reliable operation of the grounding system be ensured, providing a solid foundation for the safety and stability of the distribution network.