I. Get the Capacity Right: It's About Load Factor, Not Just "Extra Margin"
Capacity (measured in kVA) is not the simple sum of every equipment nameplate. You must calculate the demand load first. This is where most buying mistakes start.
Calculate, Don't Estimate
The core formula:
Example: A factory has 800 kW of equipment (including a 500 kW motor), power factor 0.8, diversity factor 0.8. Demand load = 800 × 0.8 ÷ 0.8 = 800 kVA. Round up to the next standard size: 1000 kVA.Required capacity S (kVA) = Total power (kW) × Demand factor × Diversity factor ÷ Power factor (cos φ)
- Demand factor: close to 1.0 for continuous loads; 0.3–0.5 for intermittent ones.
- Diversity factor: 0.7–0.9 for motor/power loads; 0.8–1.0 for lighting and heating.
- Power factor: 0.7–0.8 without reactive power compensation; 0.9–0.95 with compensation.
- Quick rule of thumb: usable power (kW) ≈ capacity (kVA) × 0.8.
| Load factor | Consequence |
| Below 30% | High no-load loss share; energy and capital wasted |
| Above 85% | Excessive heat, shorter life, tripping on peaks |
| 45%–70% (ideal) | Best balance of efficiency and service life |
Fluctuating loads (shift work, large day/night commercial swings): size to the average load and rely on short-term overload capability for peaks — don't size to the peak.
Growing loads (planned expansion): phase your investment, or leave 10%–20% headroom. More than 30% oversizing isn't economical.
Seasonal loads (HVAC, heating): handle with load management and parallel operation strategy.
Special corrections: for every 1,000 m of altitude, derate ~5%–10%; above 40 °C ambient, derate ~0.5% per extra degree.
Tip: Capacities follow standard IEC series steps (e.g. 400, 500, 630, 800, 1000 kVA). When your figure falls between two steps, round up rather than down — but check the resulting load factor. If rounding up drops you below 40%, recalculate instead.
This is the fundamental fork in the road. The real difference lies in the insulation and cooling medium, which drives every other trade-off.
| Factor | Oil-Immersed | Dry-Type (Cast Resin) |
| Insulation / cooling | Mineral insulating oil | Air + epoxy resin |
| Fire safety | Leakage and fire risk; fire protection required | Oil-free, flame-retardant, self-extinguishing |
| Heat dissipation | High (oil has high heat capacity) | Moderate; large units need forced-air cooling |
| Overload capacity | Strong short-term overload margin | Moderate (natural cooling overheats more easily) |
| Best environment | Outdoor, substations, dedicated rooms | Indoor: commercial buildings, metros, hospitals, data centers |
| Maintenance | Periodic oil testing and replacement | Nearly maintenance-free (clean dust only) |
| Initial cost | Lower | Higher (epoxy resin) |
| Service life | 20–30 years | 15–25 years |
| Typical price gap | — | 30%–50% more than oil-immersed at same capacity |
VI. Pre-Purchase Checklist: Avoid These 6 Common Mistakes
| Common Misconceptions | The Correct Way |
| Sized by adding nameplate ratings | calculate demand load properly |
| Oversized "just to be safe" | stay inside the 45%–70% load factor band |
| Skipped reactive-power compensation before sizing | define compensation first, then capacity |
| Compared on purchase price alone | calculate 10-year total cost of ownership |
| Ignored impedance voltage | 4% for lighting, 5%–6% for motors; ≤10% difference for parallel units |
| Bought uncertified or falsely rated units | insist on type test reports and compliance certificates |
Transformer selection is calculated, not copied. Compute the real load, validate it with the load factor, pick dry-type or oil-immersed by application, confirm every key parameter, then make the long-term judgment on material, efficiency, and service. Reliable load data is what keeps the whole specification honest.
